This library will help navigate a directed acyclic graph (DAG).
The goal of this library is to make it easy to:
- Find a specific node within a graph.
- Find all nodes on a certain level of the graph.
- Find all nodes between two levels of the graph.
- Find all nodes related to a given node. (i.e. find its decedents and/or its precedents on any level of the graph.)
- Sort the nodes in topological order
- Descendants. i.e. What descends from or comes after: Child
- Precedents. i.e What precedes, or comes before: Parent
- Level. We consider level as topological level of the node. I.e. Level 1 consists of nodes whose Precedents are of Level 0. In general level is the longest path from the node to the root of the graph.
publicinterfaceIGraph<T>whereT:IEquatable<T>{INode<T>Find(Tvalue);voidAddSequence(IEnumerable<T>sequence);voidAddSequences(IEnumerable<IEnumerable<T>>sequences);IEnumerable<INode<T>>Nodes{get;}boolCanSort();boolCanSort(IEnumerable<T>sequence);intCountNodes{get;}intCountLevels{get;}IOrderedEnumerable<INode<T>>GetNodes(intlevel);IOrderedEnumerable<INode<T>>GetNodesBetween(intlevelFrom,intlevelTo);IOrderedEnumerable<INode<T>>Sort();}Note:
AddSequence(IEnumerable<T> sequence): the sequence must contain at least 2 items. The relationship between the items is automatically assumed as item1 -> item2 -> item3 etc...
publicinterfaceINode<T>whereT:IEquatable<T>{TValue{get;}IGraph<T>Graph{get;}intLevel{get;}// relativeLevel >= relativeLevelFrom && relativeLevel <= relativeLevelToIOrderedEnumerable<INode<T>>GetNeighbours(intrelativeLevelFrom,intrelativeLevelTo);// relativeLevel < 0IOrderedEnumerable<INode<T>>Precedents{get;}// relativeLevel > 0IOrderedEnumerable<INode<T>>Descendants{get;}// relativeLevel == relativeLevel - 1IOrderedEnumerable<INode<T>>ImmediatePrecedents{get;}// relativeLevel == relativeLevel + 1IOrderedEnumerable<INode<T>>ImmediateDescendants{get;}// Precedents of the node without precedents (roots)IOrderedEnumerable<INode<T>>TerminatingPrecedents{get;}// Descendants of the node without descendants (leafs)IOrderedEnumerable<INode<T>>TerminatingDescendants{get;}}Note:
- All the methods return an ordered enumerable of INode. The ordering is based on the "level" of the node. (Within a level the ordering is not important.)
- If possible the methods returns all the INodes lazily.
- A Node object has a reference to the Graph object.
The Dependency Graph is a static data structure. All the nodes and their relationships should be known ahead of time.
| Method Names | Algorithms | Time Complexity |
|---|---|---|
| AddSequence() | - | O(1) |
| AddSequences() | - | O(1) |
| Sort() | Topological Sort | O(V+E) |
| CanSort() | Topological Sort | O(V+E) |
| ComputeLevels() | Critical Path, DFS | O(E+V) |
| CountNodes() | - | O(1) |
| CountLevels() | - | O(1) |
| GetNodesWithLevel() | DFS | O(V+E) |
| GetNodesWithLevelBetween() | DFS | O(V+E) |
| Precedents() | DFS | O(V+E) |
| Descendants() | DFS | O(V+E) |
| ImmediatePrecedents() | DFS | O(V+E) |
| ImmediateDescendants() | DFS | O(V+E) |
| TerminatingPrecedents() | DFS | O(V+E) |
| TerminatingDescendants() | DFS | O(V+E) |
ComputeLevels method performs initial pre-calculation (e.g. pre-calculate levels for nodes) Graph will be rebuild automatically on first call of any method related to node levels after a graph structure change.
- Find the longest path. Critical path method O(V+E)
- DFS from the source of the longest path, decrementing the level value for every child DFS - O(V+E)
#####NOTE:
- The root nodes are 11 and 12.
- The leaf nodes are 61 and 62
- This graph has 6 levels.
- The root nodes have a level value equal to 0
newGraph(new[]{new[]{11,27,32},new[]{12,27},// etc....});Or
vargraph=newGraph();graph.AddRange(new[]{new[]{11,27,32},new[]{12,27},// etc....});[Test]publicvoidBasicOperationsTest(){vargraph=CreateExampleGraph();Assert.IsTrue(graph.CanSort());Assert.AreEqual(20,graph.Count);Assert.IsTrue(graph.CanSort());Assert.AreEqual(6,graph.CountLevels);AssertCollectionsConsistsOfNodes(new[]{31},graph.GetNodes(4));AssertCollectionsConsistsOfNodes(new[]{51,61,62},graph.GetNodesBetween(4,5));AssertCollectionsConsistsOfNodes(new[]{11,12,25,26,27},graph.Find(32).Precedents);AssertCollectionsConsistsOfNodes(new[]{51,61,62},graph.Find(43).Descendants);AssertCollectionsConsistsOfNodes(new[]{25,26,27},graph.Find(32).ImmediatePrecedents);AssertCollectionsConsistsOfNodes(new[]{51},graph.Find(43).ImmediateDescendants);AssertCollectionsConsistsOfNodes(new[]{11,12},graph.Find(32).TerminatingPrecedents);AssertCollectionsConsistsOfNodes(new[]{61,62},graph.Find(43).TerminatingDescendants);}- How to return all nodes between two levels that relate to a certain node.
GetNodesRelatedTo(Tvalue,intminLevel==0,intmaxLevel== max)
graph.GetNodesRelatedTo(11,1,3)=>new[]{27,32,46}graph.GetNodesRelatedTo(32,0,3)=>new[]{11,12,25,26,27,32,46}- Node.GetNext()
- Node.GetPrevious()
- There are some ways how we can improve CanSort(sequence) method:
- We can copy graph much faster if we will find relations using temporary array and node.Key.
- We can track changes, which were made to graph and UnDo them after the sorting.